News and references from transport, lifting technology & construction

Operation reports and news from Felbermayr

Der Portalkran wurde mittels SPMT an den Zielort transportiert

Felbermayr-Engineered Solutions moves gantry crane with self-propelled vehicle

18/12/2020

In mid-December, Felbermayr relocated an approximately 18-metre-high gantry crane in the port of Duisburg. Thanks to a solution from Felbermayr's new Engineered Solutions division, it was possible to…

Strassenbauarbeiten auf einer Brücke

Civil Engineering for bridge refurbishment

17/12/2020

A 57-year-old bridge in the Hausruckviertel in Upper Austria needed to be renovated. To continue to make safe passage of the bridge possible, Felbermayr Technical Civil Engineering was commissioned to…

Der Strassenabschnitt musste für den Transport gesperrt werden

Bridge brought in with SPMT

30/11/2020

In mid-November, a 750-tonne bridge was fast tracked into place, so to speak. However, the heavy-duty equipment used was not a crane, but two SPMTs, referred to as “Self-Propelled Modular Trailers”.…

Die Brücke wurde mit mehreren SPMT eingefahren

“ENGINEERED SOLUTIONS” – Felbermayr starts a new division

29/11/2020

Supported by the areas of crane hire and heavy transport, Felbermayr has already been an important partner for heavy-lift handling when it comes to heavy equipment installation for some time; nearly…

Die Pressen wurde mittels Hafenkran vom Schiff gehoben

Relocation of presses as a team effort

05/11/2020

Concentrated know-how was demonstrated by the Felbermayr subsidiary Wimmer during the relocation of a press for the production of steel rims for the automobile industry. The Wimmer employees received…

Schwertransport, Bau-Trans, bautrans, Kessel, Suben

Dual heavy transport by water and road

19/10/2020

For a German mineral oil company, the Felbermayr subsidiary Bau-Trans transported a waste heat boiler weighing almost 100 tonnes from Nüziders in Vorarlberg towards Germany in mid-September. In…

Das Hubgerüst brauchte das Bronzepferd in seine Endposition

A 10-tonne bronze horse erected with a lifting frame

27/08/2020

Felbermayr Linz was assigned a heavy transport order with a historical background. In mid-August, the bronze casting of Alexander the Great’s legendary warhorse Bucephalus was transported to the…

Der Schiffskran versetzt die Stahlbetonträger

Record length push convoy

14/08/2020

At the beginning of August, a large-capacity push barge was used to ship concrete parts with a total weight of 500 tons from Felbermayr Wasserbau in Vienna. The prefabricated parts are required for a…

Mit dem Arbeitsgerät konnten alle Fenster des Gebäudes erreicht werden

A world first with 70 meter working height

28/07/2020

The new F-70 LTK work platform, a world first in lifting technology, recently brought the Felbermayr operating personnel and two employees of a cleaning company up into the air. In doing so, a…

Heavy transport for environmentally friendly energy

02/07/2020

A total of 16 pressurised heat accumulators, each weighing 90 tonnes, were transported from Rain am Lech to Cottbus for the conversion of a combined heat and power plant from lignite to gas operation.…

Die Klappkonstruktion wurde mit einem Kranschiff eingehoben

Crane ship for bridge construction in use

28/05/2020

In May, the crane ship from Felbermayr hydraulic engineering was used for the construction of a temporary bascule bridge for pedestrian and bicycle traffic. The installation became necessary due to…

Der Sondertransport mit der Presse kommt am Zielort an

Lifting frame used for fruit press installation

28/04/2020

In mid-April, the heavy equipment installation team from Felbermayr was called in to replace a fruit press weighing around 25 tonnes. The setting was the factory of the Austrian fruit juice producer…